New Largo Offloading Facility

A dedicated coal truck-offloading facility feeding pre-certified coal into the Kusile
stockyard.
1. Scope
MTI Engineering was awarded a contract for the Project Management, Procurement,
Fabrication, Erection, and Installation of Structural, Mechanical, and Plate Work
components.
2. Collaboration and Timeline
The project was executed in collaboration design, earthworks, civil, and electrical
teams, ensuring timely delivery within the allocated schedule. The project
commenced on 23 October 2023, with completion targeted for 13 May 2025,
including the commissioning of the Tariff Sampling Station and Audit Bin. The “First
Coal” milestone was achieved on 5 December 2024.
3. System Overview
Main Conveyors:
Conveyor P02-CVY-0615 – 976 m
Cross Conveyor P02-CVY-0613 – 145 m
Conveyor P02-CVY-0615A – 157 m
Truck Tipping Stations 1 & 2: 100t capacity, designed to accommodate coal
deliveries by trucks operating 16 hours per day, 6 days a week, for 51 weeks
annually
Sampling Station: Continuous sampling station installed on Conveyor 615, supported
by a 100 m feed conveyor.
Audit Bin & Conveyor: Installed an Audit Bin and associated conveyor system on
Conveyor 615A for verification of mass‑meter readings to ensure accuracy and
compliance

org_2c37e9da56bc5408_1732193716000.jpg
IMG20250116085443.jpg
org_584b833c440deb38_1741851108000.jpg
org_7b9d4e17edc2e58a_1741854300000.jpg

MTI Engineering

Home

Projects

Contact Us

 

TEL: +27 (0)18 786 1210
 

16 Kleim Street, Industrial Area, Carletonville, 2500, South Africa

bottom of page